Project: Edenbridge Leisure Centre
Size of Pool: 50 m2
Existing Unit: Heat Pump
Date of Installation: 1988
Reason for Change: Disrepair
Replacement Unit: VF200
   
Programme of Works:
Remove old unit: 2 Days
Install new unit: 4 Days
Modify ductwork: 3 Days
   
Total Installation Time: 9 Days

RECOTHERM LTD

1437 Pershore Road
Stirchley
Birmingham
B30 2 JL

Phone: 0121 433 3622
Fax: 0121 433 3601
Email: sales@recotherm.co.uk

When Sevenoaks District Council took over the management of Edenbridge Leisure Centre in January 2001, after it had been under private management for 5 years, they were shocked to find that the air handling plant had fallen into disrepair due to a lack of maintenance. The problem was so acute that a decision was taken to replace the unit.

The main problem facing the council was that access to the plant room was limited. So when Recotherm advised that their state of the art fresh air ventilation unit could be constructed on-site they were delighted. The whole project took 9 days to complete including removing the existing heat pump unit and modifying the ductwork to suit the new unit. Peter Kemp of Sevenoaks District Council commented that the unit had dramatically improved the internal conditions in the pool hall.