RECOTHERM LTD
CASE STUDY
 

Project: New Maldon Leisure Centre

 Size of Pool              450 m2

 Pool Volume             3780 m3

 Pool water temperature     29 ªC

 Pool hall Temperature     30 oC

 Contractor Gratte Manley Ltd

  Unit                          CVF 600

 Air volume                6 m3/s

 Maximum dehum       251 kg/h

 Year of installation     2003

 

 

 

 

 

 

 

RECOTHERM LTD

1437 Pershore Road
Stirchley
Birmingham
B30 2 JL

Phone: 0121 433 3622
Fax: 0121 433 3601
Email: sales@recotherm.co.uk


  NEW MALDON LEISURE CENTRE

The council were not happy with the performance of the existing unit and were concern how much it was costing to service. Recotherm were asked if it would be possible to replace the existing unit without having to disturb the building structure. The original unit was cut up and removed from site, the new unit was brought on site in flat pack form and assembled in position. After slight modifications to the existing ductwork and pipework systems the unit was commissioned and set to work. The whole project was completed in two weeks.  

 

The cost of servicing the unit has been reduced to £400.00 per annum.