

Due to the operational and reliability issues of the existing Dantherm unit, Recotherm were appointed to carry out the replacement of the swimming pool ventilation air handling unit.
Following the feasibility and design approvals the existing unit was isolated, made safe, and then stripped out and removed from site.
Recotherm provided a new ventilation unit in a flat pack form. This was constructed on-site within the plantroom eliminating the need for expensive builders works. Upon completion of the construction the existing ducting was modified to suit the arrangement of the VFHE unit.
Modification to the LTHW pipework and electrical distribution were also carried out.
Completion of the installation followed with the set-up and commissioning of the new unit, the pool hall internal environment is now extremely good and in-line with design intent.
Project:Holiday Inn, Gloucester
Reason for Change: Dantherm unit ineffective and unreliable
Existing Unit: Dantherm XVV
Replacement Unit: Recotherm VFHE 200
Pool
Size of Pool: 112 m²
Pool Volume: N/A
Pool Water Temperature: 30 °C
Spa
Spa Volume: 4 m³
Spa Temperature: 35 °C
Pool Hall
Pool Hall Volume: 2047 m³
Pool Hall Temperature: 30 °C
Consultation
Consultant: N/A
Unit: N/A
Air Volume: N/A
Maximum Dehum: N/A
Date of Installation: 10/01/2011
Programme of Works
Remove Old Unit: 2 days
Install New Unit: 4 days
Modify Ductwork: 4 days
Total Installation Time: 14 days